Zinfra wins upgrade works at Seqwater’s Mt Crosby Water Treatment Plant
Zinfra wins upgrade works at Seqwater’s Mt Crosby WTP

In early March, Zinfra was awarded a contract for upgrade works at Seqwater’s Mt Crosby Water Treatment Plant (WTP) in Brisbane.
 
The Mt Crosby WTP is an essential part of Seqwater’s water supply network, which provides a safe, secure and reliable water supply to south east Queensland.

The contract was awarded after months of early tender involvement with the client, including an extensive design consultation process. 

The multi-staged tender process included presenting 30% of the design of the plant, pricing, several interviews and a third party review.  According to the client, we have brought the most value to the table for through innovative and value-adding design

The scope of the work includes design, construction and commissioning of alum dosing and flash mixers, as well as a new Plant Logic Control (PLC) system, which provides electrical automation for the plant.

Peter Bierton, Senior Project Manager at Zinfra, described the purpose of the works as “disaster-proofing the plant so supply of water won’t be at risk for southeast Queensland”. 

The brownfield project has begun in March and is scheduled for completion in October 2015.

For more information, contact Peter Bierton on 0408 110 740